The Brihanmumbai Municipal Corporation (BMC) has set January 31, 2027, as the deadline to complete the Nehru Science Centre to Nehru Planetarium flyover and subway project in Worli, with Additional Municipal Commissioner (Projects) Abhijit Bangar directing officials to speed up the remaining work.
Bangar inspected the project site on Wednesday and reviewed the current status, progress, and next steps for the flyover and subway being constructed between Nehru Science Centre and Nehru Planetarium. He directed officials to increase the pace of work and ensure that the flyover is completed by January 31, 2027.
🔷वरळी येथील नेहरू विज्ञान केंद्र ते नेहरू तारांगण दरम्यान बृहन्मुंबई महानगरपालिकेतर्फे (BMC) उड्डाणपूल व सब वे बांधण्यात येत आहे. अतिरिक्त महानगरपालिका आयुक्त (प्रकल्प) श्री. अभिजीत बांगर यांनी आज प्रकल्पस्थळास प्रत्यक्ष भेट देऊन पाहणी केली.तसेच, विविध कामांची सद्यस्थिती आणि… pic.twitter.com/bXneK0Oy2e
— माझी Mumbai, आपली BMC (@mybmc) September 30, 2026
On the Nehru Science Centre side, the main piling work involving piles with a diameter of 1,200 mm has been completed. Of the 18 pile caps, 17 have been completed, while 17 of the 18 piers and 17 of the 18 pier caps have also been completed.
On the Jijamata Nagar side, the 1,200-mm-diameter main piling work has been completed. All 17 pile caps, 17 piers, and 17 pier caps have been completed.
The construction of portal beams and girder spans is currently underway at the project site and the fabrication centre. All 14 portal beams have been completed, while 17 of the 18 girder spans have been completed. Work on the remaining girder span is in progress.
The construction of portal beams and girder spans is also progressing. Thirteen of the 14 portal beams have been erected, while nine of the 18 girder spans have been erected. Deck slab concreting has been completed for seven of the 18 spans, with concreting for another two spans currently in progress.
Flyover expected to cut travel time by around 15 minutes
The proposed flyover is expected to reduce travel time for motorists using the route by around 15 minutes.
At present, motorists travelling along the route have to take a detour from Worli Naka, also known as Acharya Atre Chowk.
Once completed, the flyover is expected to provide a more direct route from E Moses Road towards Annie Besant Road and the Dharmaveer Swarajya Rakshak Chhatrapati Sambhaji Maharaj Coastal Road. Vehicles coming from Lower Parel, Mahalaxmi, and Curry Road will also be able to use the flyover directly.
The civic body said the project is expected to help reduce traffic congestion in the Worli Naka area. The reduction in travel distance and congestion is also expected to help motorists save fuel.
During the inspection, Bangar directed officials to ensure proper planning of manpower, machinery, and other resources required to complete the remaining work within the stipulated timeline. He also asked officials to increase the pace of construction and ensure coordination among various departments involved in the project.
Bangar further directed officials to coordinate with the traffic police and prepare a traffic management plan for the project.
Chief Engineer (Bridges) Rajesh Mule and other concerned officials and engineers were present during the inspection.