The first two phases of the Airoli-Katai Naka Corridor are nearing completion, with the Mumbai Metropolitan Region Development Authority (MMRDA) reviewing the remaining construction and safety-related works along the route.
MMRDA Commissioner Dr Sanjay Mukherjee inspected the entire stretch to assess the completed road infrastructure, ongoing finishing works, and safety measures near the tunnel approaches, as per the official statement.
A faster, safer commute between Navi Mumbai and the Kalyan–Dombivli region is taking shape! Imagine saving 30–45 minutes on your daily commute. MMRDA’s Airoli–Katai Naka Corridor is designed to deliver this benefit while shortening travel distances by 7–8 km. With Phases 1 and 2 in their final stages of readiness, Dr. Sanjay Mukherjee, IAS, Metropolitan Commissioner, MMRDA, undertook an inspection drive along the entire stretch, reviewing the completed road infrastructure, ongoing finishing works and progress of safety measures along the tunnel approaches. Alongside the finishing works, special emphasis is being placed on slope stabilisation and protective measures around the tunnel approaches to enhance long-term safety, monsoon resilience and all-weather connectivity. The Metropolitan Commissioner directed all stakeholders to expedite the remaining works while ensuring the highest standards of quality and safety. Combining a 1.69-km twin tunnel with elevated road sections, Phases 1 and 2 are being readied for simultaneous opening, connecting Airoli to NH-04 at Mumbra and providing an alternative to travelling via Airoli city, Thane-Belapur Road, Mahape, Shil Phata and Kalyan Phata. With Phase 3 extending the corridor to Katai Naka, the complete corridor will redefine connectivity between Navi Mumbai and the Kalyan–Dombivli region. Saving time. Strengthening connectivity. Prioritising safety. #MMRDA #AiroliKataiNaka #MumbaiInMinutes #ReshapingMMR #SafeAndSeamlessConnectivity @Dev_Fadnavis @mieknathshinde @DrSanMukherjee
— MMRDA (@MMRDAOfficial) November 24, 2026
While posting on social media handle X, MMRDA said that the inspection covered slope stabilisation and protective measures around the tunnel approaches. These works are intended to address safety concerns, particularly during the monsoon, and ensure connectivity in different weather conditions.
During the inspection, MMRDA chief Mukherjee also directed the agencies involved to expedite the pending works while maintaining quality and safety standards.
Twin tunnel and elevated road sections
Phases 1 and 2 of the corridor include a 1.69-km twin tunnel and elevated road sections. The two phases are being prepared for simultaneous opening and will connect Airoli to NH-4 at Mumbra.
The corridor is expected to reduce the travel distance between Navi Mumbai and the Kalyan-Dombivli region by approximately 7-8 km. According to the MMRDA, commuters could save around 30-45 minutes compared with the existing route.
At present, motorists travelling between these areas use routes passing through Airoli city, Thane-Belapur Road, Mahape, Shil Phata, and Kalyan Phata.
Phase 3 to extend corridor to Katai Naka
The first two phases will provide connectivity between Airoli and NH-4 at Mumbra, while the third phase will extend the corridor to Katai Naka.
MMRDA said, “Alongside the finishing works, special emphasis is being placed on slope stabilisation and protective measures around the tunnel approaches to enhance long-term safety, monsoon resilience, and all-weather connectivity.
The complete corridor is expected to provide an alternative road connection between Navi Mumbai and the Kalyan–Dombivli region.
“Combining a 1.69-km twin tunnel with elevated road sections, Phases 1 and 2 are being readied for simultaneous opening, connecting Airoli to NH-04 at Mumbra and providing an alternative to travelling via Airoli city, Thane-Belapur Road, Mahape, Shil Phata, and Kalyan Phata.” MMRDA further added.